Despite the ongoing challenges caused by the war, the Novy Zodchy continues construction work on four projects in Kyiv and Dnipro. Today, our team has also begun work on a new office center in Lviv.

To our prospective clients, we would like to assure you that we have the necessary capacity and remain fully committed to delivering on our obligations under any circumstances.

We welcome the opportunity to collaborate.

Service Point ProCredit Bank
29January2025

The company Novу Zodchу completed the construction work for "Service Point ProCredit Bank" at the Respublica Park shopping mall. Today, the project has been successfully handed over to the client. We continue to work and fulfill our commitments.

паспортний сервіс у Германії
05August2024

At the end of July, the company Novу Zodchу handed over the next project to the Client - the ProCredit Bank office center at 26 Lvivska, Kyiv.

The following works were completed:

  • a complex of repair and finishing works;
  • installation of internal engineering networks;
  • manufacture and installation of furniture.

The Client highly appreciated the efficient and quality work.

passport service in Germany
22April2023

According to experts, the construction company NOVY ZODCHY successfully penetrates the markets of EU countries and makes a significant contribution to the Eurointegration program. In a short period, we have completed the design and construction of office centers PASSPORT SERVICE in Warsaw, Krakow, Gdansk, and Wroclaw in Poland. The customer and numerous clients highly appreciated our work!

passport service in Gdansk
09January2023

Construction company NOVY ZODCHY continues to explore the markets of European Union countries. After the successful completion of the PASSPORT SERVICE project in Warsaw, our team has designed and built a similar facility in Gdansk, which opened on December 30, 2022. The next projects include designing and constructing facilities in Krakow and Wroclaw.

passport service in Warsaw
23August2022

Construction company NOVY ZODCHY is exploring the markets of European Union countries. Our modest contribution to the Eurointegration program includes the design and construction of the PASSPORT SERVICE office center, which opened in Warsaw. In the near future, we will hand over projects in Krakow, Gdansk, Wroclaw, and in perspective – in other EU countries.

repair work at ProCredit Bank
25January2022

To enhance competitiveness in the banking segment, NOVY ZODCHY completed the implementation of the ProCredit Bank project – a large and high-tech branch at 67 Peremohy Avenue, Kyiv. The customer was pleased with effective management, a systematic approach, and the high qualifications of the staff. As the general contractor and executor of the works, the NOVY ZODCHY group gained trust with impeccable performance of its obligations. Our experience in the banking segment includes 47 branches and offices of 14 leading banks in Ukraine!

repair work at Respublika Park shopping mall
12November2021

On November 12, 2021, the grand opening of the largest shopping mall in Ukraine, Respublika Park, took place. We are pleased to announce that NOVY ZODCHY took part in the preparation of this festive event: in the shortest possible time, in coordination with tenants, we completed a complex of works on machine-floor screed installation. Our company guarantees high-quality work!

repair work at Alfa-Bank office
14October2021

Another achievement of NOVY ZODCHY in the banking segment: AHUB KYIV "ALFA-BANK", Yaroslaviv Val Street, 7. The works were performed with high quality and, as always, on time. The customer also noted the versatility, organizational flexibility, and management efficiency. AHUB KYIV is the creative search of ALFA-BANK for attracting clients to a new creative space. It is simultaneously a super-modern coworking space, convenient conceptual negotiation rooms, a conference hall, and a unique Sense Room.

construction of the main building of Darnitsa pharmaceutical company in Kyiv
16June2021

The grand opening of the object - the Main Administrative Building of PJSC "Pharmaceutical Firm "Darnitsa" - took place on June 16, 2021. Developing its competitive advantage - VERSATILITY - the company NOVY ZODCHY successfully fulfilled the obligations of the GENERAL CONTRACTOR and the MAIN WORKS PRODUCER. The approach from the customer and the company "KDD Engineering," which carried out technical supervision, was organized and met the level of international class. The result satisfied the high requirements of the management and owners of PJSC "Pharmaceutical Firm "Darnitsa." We appreciate the new experience of high standards and are proud of our work!

reconstruction of GooDWine network store-restaurant
14June2021

NOVY ZODCHY successfully completed the reconstruction of the fashionable store-restaurant flagship of the GooDWine network in Kyiv, Mechnikova Street, 9. Fans of the noble drink appreciated the external and internal design of the "small empire of tasty life." The customer highly appreciated our work and proposed to continue cooperation.

construction work at Passport Service branch in Kyiv
20April2021

The opening of the new office center PASSPORT SERVICE in Kyiv, Bazhana Avenue, 38. As the representative of the customer noted: "NOVY ZODCHY is a universal company with the quality mark that provides comprehensive solutions: design, general contracting, a full range of construction works, equipment installation, furniture manufacturing, and service maintenance. This is an important competitive advantage, and we recommend NOVY ZODCHY as a professional general contractor and a reliable performer of works." Modestly, we add: this is the 25th office center of the national network of the state enterprise "Document" implemented by our group.

repair work at ProCredit Bank branches
15March2021

The opening of digital banking branches in the largest shopping malls in the capital: BLOCKBUSTER MALL, SKYMALL, ALADDIN, RETROVILLE. The progressive solution of the ProCredit Bank management - from project to implementation - was implemented by the NOVY ZODCHY group. The branches are made in a modern laconic design, allowing the introduction of digital technologies into a qualitatively new customer service. Our work received high praise.

New ZODCHI Group results for 2020
12January2021

Summing up the results of 2020, it should be noted that the NOVY ZODCHY Group achieved good results: the volumes of completed works increased by 11%, the number of simultaneous objects in production increased by 12.5%, and financial and economic indicators improved. Our experience, competent team, high corporate culture, and grateful clients allow us to confidently look to the future.

complex of repair and construction works at GRAND ADMIRAL RESORT & SPA
25September2020

The NOVY ZODCHY Group, as part of cooperation with GRAND ADMIRAL RESORT & SPA, hands over another object: the third building (we handed over the first two last year) of the International School of English STUDY ACADEMY. The customer happily noted the successful result and wished our team success and prosperity.

complex of repair and construction works at ProCredit Bank
09September2020

The company NOVY ZODCHY, as the general contractor and the main performer of works, completed the repair and construction works at the TRAINING CENTER of ProCredit Bank at the address: Kyiv, Kotelnikova Street, 49. The customer, thanking, noted the efficiency of management and the high quality of work.

complex of repair and construction works at the State Historical and Cultural Reserve Tripilska Culture
03September2020

NOVY ZODCHY completed the execution of a significant in size and historical importance complex of repair and construction works at the State Historical and Cultural Reserve "Tripilska Culture." For us, as for every enlightened citizen, this object has special significance, and we are proud of the high assessment of our work.

construction work at ProCredit Bank
18June2020

BC "Novу Zodchу" started construction work on a new object of JSC "ProCredit Bank" in the SAN-FRANCISCO-CREATIVE-HOUSE shopping and business complex, Kyiv, Prospekt Peremohy, 67. The customer's trust is a key criterion for the competitiveness of our team and an additional incentive for impeccable fulfillment of obligations.

reconstruction work at the main Kyiv branch of UKRGASBANK
19May2020

Reconstruction work at the main Kyiv branch of UKRGASBANK on Staronavodnitska Street, 19, 21, 23, has been completed. The bank's management positively evaluated the results of our work as the general contractor and the main performer of the works and expressed the intention to continue cooperation.

repair of premises at ProCredit Bank
20February2020

Work on the repair of premises, improvement of the adjacent territory, and the arrangement of a car park has been completed at the main office of JSC "ProCredit Bank" at 107A Peremohy Avenue, Kyiv. The management and employees of the bank positively assessed the results of the work of the construction company "Novу Zodchу" and proposed to continue cooperation.

Reconstruction of the administrative building of UKRGASBANK
19December2019

Permission has been obtained for the reconstruction of the UKRGASBANK facility at: Kyiv, Staronavodnytska Street, 19, 21,23. The construction company NOVY ZODCHY is the general contractor and the main performer of the works.

Reconstruction of the administrative building of PJSC Pharmaceutical firm DARNYTSIA
09December2019

Bidding for the selection of the general contractor for the object: "Reconstruction of the administrative building of PJSC Pharmaceutical firm DARNYTSIA" - 27 contenders participated - ended with the victory of the construction company "NOVY ZODCHY". In accordance with the general contract, work has begun - a great honor, high responsibility, a new stage of improvement.

execution of a complex of construction works in the innovative residential complex METROPOLIS
24September2019

The construction of new symbols of the capital: Taryan Towers, JACK HOUSE, Signature, AVTOGRAF, Busov Hill, Linden has a worthy continuation: a general contract has been signed with the leading developer of the capital - DIM company - for the execution of a complex of construction works in the innovative residential complex METROPOLIS.

execution of a complex of design and construction works in the SAN-FRANCISCO-CREATIVE-HOUSE residential complex
29July2019

On 29.07.19, a general contract was signed between ProCredit Bank and NOVY ZODCHY, which provides for the execution of a complex of design and construction works at the object: Kyiv, Prospekt Peremohy, 67 in the new SAN-FRANCISCO-CREATIVE-HOUSE residential complex. Cooperation with a large, business development-oriented bank is a great responsibility and an important criterion for compliance with the highest European standards for us.

brickwork in TARYAN TOWERS
04July2019

Multiplying the reputation of a reliable contractor for "star" objects in the capital, the "Novу Zodchу" group started work in TARYAN TOWERS - according to experts, the most innovative residential complex in the country.

15 years to the Group of companies 'Novу Zodchу'
30April2019

In April 2019, the Group of companies "Novу Zodchу" celebrated its 15th anniversary! With pride, assessing a significant result - more than 200 objects have been erected, our team, not stopping at what has been achieved, continues to develop professional skills and competitive advantages.

brickwork in the premium-class residential complex LINDEN LUXURY RESIDENCES
29March2019

On March 28, 2019, a significant volume of brickwork was successfully completed on one of the "star" objects in the capital - the premium-class residential complex LINDEN LUXURY RESIDENCES (Kyiv, Lutheran Street, 14v). Our team received high praise, positive feedback, and good recommendations from the customer. We take pride in our work!

complex of finishing and installation works at Grand Admiral Resort & SPA
29December2018

Grand Admiral Resort & SPA is our long-standing and respected customer, whose new ambitious project - a 5-star hospitality SPA hotel - has been successfully implemented by the company "Novу Zodchу". In six months of hard work as the general contractor and main performer of the works, a complex of finishing, decoration, and installation works has been completed. Elegant rooms in eco-style, using natural materials in the interior, corridors, elevator halls, a banquet hall located next to the panoramic restaurant Mozart will amaze the most demanding clients.

manufacturing and installation of light decoration on the facades of the ROSHEN Confectionery Factory
28December2018

On the eve of the New Year and Christmas holidays, the construction company "Novу Zodchу" performed a complex of works on the manufacture and installation of the "New Year's Fantasy" light decoration on the facades of the ROSHEN Confectionery Factory in Kyiv, thanks to which massive industrial buildings turned into a fabulous city. The customer positively evaluated our work, noting the creative approach, efficient organization, speed, and quality.

Construction work in the building of UKRGASBANK
20November2018

The construction company "Novу Zodchу" has started the major overhaul of the archive building of PJSC AB "UKRGASBANK". Our experience in the segment of financial institutions, including the State Treasury of Ukraine, 11 banks, 34 bank branches and offices, has been taken into account by the customer, leaving no doubt that the commitments will be fulfilled.

Construction work in the Autograph complex
08November2018

The company "Novу Zodchу" has started performing finishing and decoration works at the facility: Residential complex "Autograph," the second stage. With a high degree of probability, we consider that this contract was received due to our conscientious performance of obligations on previous projects of the development company DIM. Confirmation of the axiom: effective work - good reputation - new opportunities!

Construction work in the SIGNATURE complex
02October2018

The general construction works in the elite-class residential complex SIGNATURE, Kyiv, Mechnikova Street, 11a, which were performed by LLC "Construction Company Novу Zodchу," have been successfully completed. Traditionally - our team, having fulfilled its obligations with dignity, is marked by a high assessment and positive feedback.

Construction work on Ahmatova Street
03September2018

Reconstruction of a six-story administrative building located at: Kyiv, A. Akhmatova Street, 13-E, has been completed. Thanks to effective construction management, the expected positive result has been achieved. The customer noted: the high potential of the "Novу Zodchу" group of companies, conscientious, prompt, and high-quality work.

Construction work in Busov Hill
30August2018

The construction company "Novу Zodchу" has completed a complex of works in the premium-class residential complex "Busov Hill." Our team is praised for efficient organization, a systematic approach, and conscientious work.

Finishing and decoration works in Grand Admiral Club
30May2018

The construction company "Novу Zodchу" has started performing finishing and decoration works at the SPA HOTEL of the sports and recreational complex "Grand Admiral Club." The trust of the customer, with whom we have been cooperating for many years, is a positive assessment of our competencies: the efficiency of the general contractor's management, price, quality, and work deadlines.

Reconstruction of a house on Ahmatova Street
10May2018

Work has begun on the reconstruction of a six-story building located at: Kyiv, A. Akhmatova Street, 13-E. Implementing the idea of creating a unique modern business center, analyzing alternatives, the customer preferred our company, appreciating: a comprehensive approach (design, general contracting, work execution), optimal contractual price, and the shortest terms.

02April2018

Successfully completed construction work in the residential complex "Lypynka-2," located on Novomostytska and Zamkovetska streets. The customer (Kyivmiskbud HC) and the general contractor (LLC Ukrbudinvest) positively assessed the results of the work of the construction company "Novу Zodchу" and proposed to continue cooperation on a new project.

25January2018

The construction company "Novу Zodchу" has started work on another object of elite housing. This is a residential complex on Lutheran Street, 14-v, which has no name, as it does not need advertising. The management of the "Novу Zodchу" group, acknowledging the growing reputation in the premium segment, responsibly states: we will ensure high quality and optimal terms - commitments will be fulfilled!

27December2017

In a record-short time (12 working days), the company "Novу Zodchу" completed a full range of finishing and decoration works in the sales department - the epitome of a modern residential complex of comfort class "Metropolis" (Kyiv, Academic Zabolotny Street, 1). The company confirmed its competitive advantages, justified the trust of the customer, and gained the respect of investors.

Image of the Autograph residential complex
14December2017

The construction company "Novу Zodchу" completed contractual obligations with high quality and within the specified terms, finishing work on the first and second sections of the Autograph residential complex. The recognized and qualified general contractor, LLC "Domian," positively assessed our contribution to the realization of the project's unique idea and, expressing an intention for further cooperation, recommends the construction company "Novу Zodchу" as a responsible contractor and competent performer of works.

04December2017

The construction company "Novу Zodchу" has started work on the residential complex SIGNATURE (Mechnikova Street, 11-a). The prestigious object - an impressive symbol of the capital - sets high demands, and upon achieving them, with pride for the work done, we will put our signature (SIGNATURE - English signature).

24November2017

Within the specified terms, with high quality, a complex of finishing and decoration works has been completed in the residential complex JACK HOUSE - a 33-story club-type premium class building, Kyiv, L. Ukrainky Boulevard, 7-9. The general contractor positively assessed our work and recommends LLC "Novу Zodchу" as a responsible and competent performer of works on premium-class objects (the review is published on our corporate website).

16October2017

Long-standing business relations between the sports and recreational complex "Grand Admiral Club" and the group of companies "Novу Zodchу" are consistently and steadily developing: on October 16, 2017, the construction company "Novу Zodchу" started performing finishing and decoration works of hotel rooms. The trust of a regular customer is a positive assessment of our competencies on the path of continuous improvement.

29September2017

On September 29, 2017, the opening of the "Passport Service" office center took place in Odessa, Kateryninska Street, 27/1. We proudly note that this festive event was prepared by the company "Novу Zodchу" - design and finishing and decoration works were done with high quality and in record-short terms.

21September2017

With the aim of more complete realization of the opportunities of UBG "Novу Zodchу," a series of meetings with representatives of customers of elite housing construction was held: JACK HOUSE residential complex, Busov Hill residential complex, "Autograph" residential complex. This positive assessment of management and work quality, and proposals for expanding cooperation.

News about the opening of the Passport Service office center
12August2017

On August 12, 2017, the grand opening of the largest office center "Passport Service" in Ukraine took place at: Kyiv, Ploshcha Peremohy, 3. The universal construction group "Novу Zodchу" - designer, general contractor, and the main executor of works - fulfilled its obligations with dignity and received high marks from the management of the State Enterprise "Document," colleagues, representatives of the media, and the public.

News about the start of repair works at the Passport Service office center
3July2017

On July 3, 2017, design and finishing works began at the new office center "Passport Service" at: Kyiv, Ploshcha Peremohy, 3 (third floor of the "Universam Ukraine" shopping center). The "Novу Zodchу" team has a responsible and honorary duty: to complete a complex of works on the object, which, according to the customer's idea, should become exemplary in Ukraine, within 30 calendar days.

News about the start of repair and finishing works in the premium class residential complex Busov Hill
29June2017

On June 29, 2017, the grand opening of the new "Passport Service" office center took place in Kharkiv, Sumskaya Street, 10. The company "Novу Zodchу," as always, with high quality and within the specified terms, fulfilled its obligations.

1June2017

On June 1, 2017, the company "Novу Zodchу" began the implementation of finishing and decoration works in the premium-class residential complex "Busov Hill." The elite new building sets high requirements for management, quality, and deadlines for work, but for our team, it is an honorable duty and a new level on the path of improvement.

News about the start of work in the new office center 'Passport Service' in Kharkiv
30May2017

On May 30, 2017, the company "Novу Zodchу" began the implementation of design and finishing works in the new office center "Passport Service" in Kharkiv, Sumskaya Street, 10. This is the sixth office center of the State Enterprise "Document" (the second in Kharkiv), which our team traditionally performs with high quality and in record-short terms.

10May2017

On May 10, 2017, the company "Novу Zodchу" began the implementation of interior finishing works in the residential complex "Autograph." Like all DIM company projects, this project is significant, and it has an idea that we bring to life.

News about the grand opening of the object: 'Hearing Rehabilitation Center 'AURORA''
25April2017

On April 25, 2017, the grand opening of the object took place: 'Hearing Rehabilitation Center 'AURORA'''. The management, foreign investors, and representatives of the public noted the systematic approach of the company "Novу Zodchу" both in project development and in its high-quality execution.

22February2017

On February 21, 2017, the company "Novу Zodchу" started the general construction works in the residential complex located in the Podil district of Kyiv, on Novomytyska Street and Zamkovetska Street. The project involves the construction of nine residential buildings.

10December2016

On December 5, 2016, by the order of the Chairman of the State Architectural and Construction Inspection of Ukraine No. 45-L, the company "Novу Zodchу" was issued a license for economic activity in the construction of objects of the fifth category of complexity until 5.12.2021. This license gives the right to construction of objects of the highest category of complexity.

News about the grand opening of the office center 'Passport Service' in Uzhgorod
30November2016

On November 29, 2016, the grand opening of the office center "Passport Service" took place in Uzhgorod. The attendees, including the head of the region, the management of the State Enterprise "Document," representatives of the press, and the public, noted the importance of this event in the accessibility of services and expressed gratitude to the team of the company "Novу Zodchу" for professional organization of work and dedicated work.

20November2016

Traditionally, with high praise, on November 17, 2016, the company "Novу Zodchу" completed the implementation of interior finishing works on thirty-three floors of the elite residential complex in Kyiv – JACK HOUSE. The next stage is the decorative, in accordance with the design project, decoration of corridors and elevator halls.

20September2016

The solemn handover of the object took place – the complex of buildings of the Embassy of the Republic of Belarus in Ukraine, located at: Kyiv, Solomianska Street, 17. The team of the company "Novу Zodchу" was noted with a positive response for the quality performance of the work.

News about the opening of the office center 'Passport Service' in Kharkiv
05August2016

On July 25, 2016, the grand opening of the office center "Passport Service" took place in Kharkiv. The customer – the State Enterprise "Document" – expressed gratitude to the team of the company "Novу Zodchу" for high organization and quality work.